Commercial Ground Mount- Software Developer, Warwickshire

Description

Our client has a large office area with a high daytime demand from air conditioning, servers and office facilities for the staff. In order to reduce their carbon footprint and greatly reduce electricity costs, SSW were commissioned to construct a 300kWp solar array on sloping waste ground adjacent to the offices. This was a turn-key project from initial design, obtaining grid and planning consent, installation, commissioning and landscaping in line with planning conditions. The system is operating successfully to target.

Information

Client

Codemasters

System Size

303kWp

Output

270MWh

CO₂ saved per annum

57.2t

Modules

JA Solar 275W

Count

920

Inverter

Solis